Branson Downtown Construction 2025 — Big changes are happening in Branson’s Historic Downtown as Phase 4 of the Downtown Streetscape Project is in full swing, bringing upgrades to the area while still retaining the charm and history of downtown.
What’s Going On? Branson Downtown Construction
The latest phase kicked off on April 1, 2025, and wraps up by October 15. Construction is happening in two parts to keep businesses open:
-
Phase 1 (April – Early June): Veterans Blvd to Commercial Street
-
Phase 2 (June – October): Commercial Street to Sycamore Street
Crews are working 24/7—nights for sidewalk removal, days for building it all back better.
What’s Been Done So Far?
As of mid-May, here’s what’s checked off:
-
Sidewalks removed ✔
-
Foundations for new lights ✔
-
Decorative seat walls going up ✔
-
New water lines, stormwater boxes, and underground electrical systems ✔
What’s Coming Soon? Branson Downtown Construction
-
Wider sidewalks and better crosswalks
-
Retro-style lighting and updated landscaping
-
Stronger utility systems ready for the future
Shop & Stroll Safely
Yes, businesses are still OPEN in Downtown! Temporary gravel paths and signs make it easy (and safe) to get around. So, grab a coffee, do some shopping, and support local businesses while the dust settles!
Want Updates? Branson Downtown Construction
Want Updates?
Text DWNTBRANSON to 417-807-2075 for real-time info.